- Arts & Culture 5937
- Business & Economics 689
- Computers 310
- Dictionaries & Encyclopedias 81
- Education & Science 74674
- Abstracts 251
- Astrology 4
- Astronomy 1
- Biology 8
- Chemistry 2221
- Coursework 15546
- Culture 9
- Diplomas 411
- Drawings 574
- Ecology 5
- Economy 83
- English 75
- Ethics, Aesthetics 3
- For Education Students 17221
- Foreign Languages 11
- Geography 2
- Geology 1
- History 89
- Maps & Atlases 5
- Mathematics 13855
- Musical Literature 2
- Pedagogics 19
- Philosophy 23
- Physics 14834
- Political Science 5
- Practical Work 101
- Psychology 60
- Religion 4
- Russian and culture of speech 8
- School Textbooks 7
- Sexology 42
- Sociology 9
- Summaries, Cribs 87
- Test Answers 150
- Tests 8455
- Textbooks for Colleges and Universities 32
- Theses 24
- To Help Graduate Students 14
- To Help the Entrant 37
- Vetting 363
- Works 13
- Информатика 10
- Engineering 3058
- Fiction 696
- House, Family & Entertainment 107
- Law 132
- Website Promotion 71
Test. Project management, option 4.
Refunds: 0
Uploaded: 20.08.2013
Content: variant_4_reshenija.rar 318,33 kB
30 $ | the discount is | 12% |
15 $ | the discount is | 5% |
5 $ | the discount is | 1% |
Seller will give you a gift certificate in the amount of
Product description
Option 4
Followers Operation Predecessors duration Workforce
(Work) (days) (pers.)
A B, C April 5
B D A January 8th
C E, F, G, H A 6 0
D F, G, H B March 2
E I C June 4
F I C, D July 8
G KC, D 1 June
H J C, D March 8
IK E, F April 9
J K H 5 0
K L, M G, I, J March 6
L N K Aug. 4
M K 2 March
N O L 1 August
O N February 3
Build a network model. Run time and resource analysis
Option 4
Operation
(I, j) normal deadlines Deadlines Increased costs
Duration costs Duration costs
(0,1) -A 4210 3280 70
(0,2) -B 8400 6560 80
(1,2) -C 6 400 4.6001 million
(1,4) -D 9540 7600 30
(2,3) -E 4 800 100 January 1100
(2,4) -F 5 150 4240 90
(3,5) -G 3150 3150 -
(4,5) -H 7600 6.75015 million
= 3250 = 4280
The table shows the duration and cost of each operation corresponding to the normal and the most intensive mode of its implementation. To illustrate the effect of accelerating the work on the overall cost, we will take into account the indirect costs of $ 130 den. units / day.
Task: required to determine the minimum cost of schedules that can be implemented in the interval between the points of maximum intensity and normal modes. Find the optimal schedule.
Additional information
Option 4
Limited Liability Company «Jubilee Computer Systems Ltd» performs the order received from its customers. The required information is listed below.
Operation
The period immediately preceding the operation, days Cost for the expected duration, f. cm.
Optimistic most likely pessimistic
A 3 May 13300
In August 1 9700
C 4 5 6 2000
D A 7 8 15 1200
E 2 to 4 12900
F With 8 9 22 2300
G DE 3 April 5400
H, G, F February 1 3300
8100
Indirect costs associated with the implementation of the project amount to £ 300. Art. in a day. The contract concluded with a consumer, agreed that if the order is not made within 20 days, the amount of the penalty will be £ 100. Art. for each subsequent day. Required:
1.Postroit network graph. What is the expected value of the execution time of the entire project? What is the value corresponding to the value?
2. What likelihood that the project will be completed without payment of penalties?
3.Kakova likelihood that the project will be completed in the interval from 21 to
25 days?
Feedback
0Period | |||
1 month | 3 months | 12 months | |
0 | 0 | 0 | |
0 | 0 | 0 |